Implementation report 2019

Implementation report 2019

Implementation report 2019

Outcome

01.04.2019

Gas transmission system operators publish Implementation Report on the Gas Network Development Plan 2018-2028

A total of 16 projects worth of around €840 million set out in the Gas Network Development Plan 2018-2028 (NDP 2018) have been completed and put into service. They include three pipeline projects with a length of 113 kilometres, five compressor projects with a capacity of 146 MW and eight gas pressure regulating and metering stations.

Read more

In their Implementation Report 2019, the TSOs report on the progress of 142 projects in total while also providing information on modified, cancelled and delayed projects.

Given the importance of the ongoing L/H gas conversion for the energy industry, much of the Implementation Report is devoted to the details of the planning process. 300,000 L gas appliances have so far been successfully switched to H gas. The conversion plan has been updated and the conversion areas have been largely agreed with the DSOs until 2026. The ongoing dialogue between the German and Dutch TSOs has facilitated a harmonised approach to dealing with the assumptions in both countries.

Details on the 2019 Implementation Report are available in the NDP Gas Database (www.nep-gas-datenbank.de).

The TSOs also published today their quarterly update of the binding list of announced conversion areas, which can be found on the FNB Gas website in the Market Area Conversion section.

Show downloads     +

  • Umsetzungsbericht 2019
    Download / 2.78MB / PDF
  • PDF Pressemitteilung: Veröffentlichung Umsetzungsbericht 2019 vom 01.04.2019
    Download / 0.18MB / PDF